How should the injection molding machine be fixed

Jul 16, 2018 Leave a message

                  How should the injection molding machine be fixed?

   For small and medium - sized injection molding machines fixed installation, generally do not use anchor bolts.Only pay attention to the equipment foundation can bear the weight of the injection molding machine, and at the same time to resist vibration.During production, the equipment shall not sink, skew or tilt sideways, and resonance shall not be allowed.A flat concrete floor can be installed with shock absorber feet.

   After the cooling equipment is in place, adjust the mutual position of each equipment, pad the pads, and calibrate the level with a horizontal ruler (the level should be calibrated according to the pull rod at the guide rail and the molding part of the injection base).The plane of the equipment base should be 3 ~ 5cm above the workshop floor.

   As for some special requirements or larger injection molding machines, cement and concrete foundation should be well watered according to the specifications.Arrange the water, electricity and gas pipelines into the underground foundation before pouring the concrete according to the requirements of the foundation drawing in the specification.

   Automation equipment installation.After leveling and fastening, connect water, electricity and gas lines and install accessories for equipment.